Lakeshore Road Reconstruction and Streetscape Project Phase 2 begins January 7, 2020

Tuesday, December 24, 2019

Union Gas is scheduled to begin replacing the gas lines for phase two of the Lakeshore Road reconstruction project on January 7, 2020, the town announced today. This early start follows extensive feedback from the business community at the December 16 Council meeting to get the work done as fast as possible.

“Council has heard the messaging from our retailers, shoppers, downtown business owners, residents, landlords and is committed to complete the project as soon as possible,” Mayor Rob Burton said. “We value this level of engagement and know this $20 million dollar investment will contribute to the long-term health of our downtown.”

Council has also authorized CRCE, the general contractor on the project, to work weekends and evenings where required. Mayor Burton noted work can be done on Saturday and Sunday if a Monday-Friday work day is missed due to weather ensuring the project stays on track.

“We are all very much aware of the desire to have the project completed as soon as possible,” said Jill Stephen, Director of Engineering and Construction.  “The Lakeshore Road project is a complex one involving multiple contractors working together to complete the work required by the Town, Halton Region, Union Gas and Oakville Hydro and we will look at every opportunity to move this project forward faster.”

Council directed staff to report back to February’s Council meeting, addressing additional opportunities to shorten the completion deadline. 

Council also heard from Dorothy St. George, Director of Economic Development regarding projects included in the mitigation strategy:

Businesses are also able to apply for a $2,500 digital transformation grant from the Province until January 10, 2020, to assist in implementing new ideas.

Phase two is scheduled to begin in January, closing Lakeshore Road for vehicles from Dunn Street to Allan Street. As with Phase 1, work will begin with Union Gas replacing gas lines, followed by watermain work, replacement of electrical infrastructure and Silva cell installation. Above ground work will include concrete paving and granite curbs followed by finishes and new furniture. 

Remaining phase one work includes the installation of traffic signals at George and Lakeshore Road, new light poles as well as the removal of temporary asphalt boulevards and granite curbs. Much of the work is weather dependent and will be undertaken in the spring, 2020. Work will be completed without the need to close Lakeshore Road to vehicular traffic.